What are Alternative Solutions in the Building Code of Australia (Pre 2016)?

So what are Alternative Solutions, also referred to by some people as a ‘Dispensation’, ‘Exemption’ or ‘Performance Assessment’? These are described below and are applicable before the introduction of NCC/BCA 2016.

In BCA 2015 these are referred to as Alternative Solutions.

From BCA 2016, these are now known as what are Performance Solutions.

The National Construction Code 2015 (NCC), which includes the Building Code of Australia (BCA) (Volumes One and Two)  is a ‘performance-based’ building code.

Jigsaw Puzzle Pieces, with missing pieceAs the code is ‘performance-based’, each section of the BCA has minimum levels of compliance which are mandatory – these are called the ‘Performance Requirements’.

The Australian Building Codes Board has been quoted as stating that the use of a performance-based approach to compliance  ‘provides practitioners with a strong degree of flexibility to determine the most appropriate means for demonstrating compliance with the relevant Performance Requirements’.  This therefore allows some level of creativity in how compliance (or a compliant building solution) can be achieved and could see the introduction of new materials, technologies or methodologies, which could also see some efficiencies, better outcomes and cost savings, whilst still meeting the relevant Performance Requirement.

Methods of providing a compliant building solution are shown in the diagram below that has been adapted from the BCA.  There are three methods to achieve compliance with the Performance Requirements:

  1. complying with the ‘Deemed-to-Satisfy’ Provisions (or the prescriptive approach detailed within each part of the BCA);
  2. formulating an Alternative Solution (i.e. adopting a ‘performance-based approach’); or
  3. a combination of both of the above.

Compliance with the ‘Deemed-to-Satisfy’ provisions of BCA 2015 is easier as these building solutions are all detailed within the pages of the BCA and will be deemed to comply with the relevant Performance Requirements.

What are alternative solutions, Building Code Compliance Options, Lee Wilson

If a performance-based approach is adopted to achieve compliance an ‘Alternative Solution’ must be developed for acceptance by the building surveyor / building certifier.

An ‘Alternative Solution’ has been defined asa building solution which complies with the Performance Requirements other than by satisfying the  ‘Deemed-to-Satisfy’ provisions of the BCA.’

A simple example of an ‘Alternative Solution’ is automation of a hinged leaf door. This undoubtedly provides a better building solution and provides a greater level of accessibility for users of a building (including those with mobility limitations including reduced hand dexterity, those using a mobility aid such as a wheelchair or a walking frame, amputees etc.). This design solution does not ‘fit’ in with the ‘Deemed-to-Satisfy’ provisions and is not an option provided in AS1428.1. Therefore, it is an ‘Alternative Solution’ that must be developed and documented.

Any proposed ‘Alternative Solution’ must be documented, and verified  it complies with the  relevant Performance Requirements. The BCA details ‘Assessment Methods‘ that can be used to confirm compliance, however to ensure compliance with the Access to Premises Standards the use of Expert Judgement alone should be avoided for access related issues.

More information on preparing ‘Alternative Solutions’ is provided here.

By Lee Wilson, Disability Access Consultant / DDA Consultant, Melbourne, Victoria. Lee is an Accredited Member of the Association of Consultants in Access, Australia Inc.

Contact MAA for all your disability access consulting needs, including Performance Solutions / Alternative Solutions.

MAA B R ON WHITE-min2

Advertisements

One thought on “What are Alternative Solutions in the Building Code of Australia (Pre 2016)?”

Comments are closed.

Display Due Diligence, consider a Disability Access Peer Review by an Accredited Access Consultant during the Building Certification process

%d bloggers like this: